Dumstper #2 arrives; Shingles delivered; plumber visit; rough framing; facia

 

Shingle delivery from Wimsatt

Work done today:

  • Dumpster #2 arrived; dumpster #1 is full and is hauled away.
  • Shingle delivery
  • Mike Cole visits with plumber
  • JCJ 4-person crew (Jeremy, Rusty, Brandon & Anthony) finish interior work on back entryway and frame the doors and windows on the dining room exterior wall. Install the facia at the roof edge in preparation for shingle work.

Filled dumpster being lifted onto the truck.


While Mike was touring the plumber through the house, the Wimsatt truck showed up with the shingle delivery.


Shingles delivered to the roof.

Long reach for shingles over the dumpster.

2:00pm
Framing the windows and doors on the back wall.

Note the new, white facia trim around the perimeter of the roof.